Beijing, Mar 18: China has dismissed as fake news rumours about sending troops to Russia, including a cropped picture showing a fully-loaded Chinese military truck convoy at the border with Russia, according to a media report on Friday.

A photo circulating on Twitter is a cropped version of a picture first published in 2021, China's internet watchdog said.

China had earlier denied reports that Russia had asked it for military support in its Ukraine military offensive.

The Cyberspace Administration of China (CAC), the country's internet watchdog, said on Thursday that there were many fake news reports online aimed at discrediting China's position on the war in Ukraine, the Hong Kong-based South China Morning Post reported on Friday.

A photograph of a long line of fully-loaded Chinese military vehicles travelling at night has circulated on Twitter, triggering speculation that China was providing assistance to Russia.

But it was actually an edit of an old shot from May 2021, the CAC said.

A tweet had said a photo of 200 to 300 People's Liberation Army (PLA) trucks was taken by a local driver on March 14 in the north-eastern Heilongjiang province, near Suifenhe, a town on the border with Russia.

The original photo was an official publicity shot of a PLA regiment's night transport exercise in the western region of Xinjiang last year, which was first published in the official PLA Daily on May 10, 2021, the CAC said.

Let the Truth be known. If you read VB and like VB, please be a VB Supporter and Help us deliver the Truth to one and all.



Bengaluru: The Karnataka High Court has quashed a May 20, 2022, National Green Tribunal (NGT) order that held the Madras Engineering Group (MEG) and Centre, Bengaluru, responsible for pollution in Halasuru Lake.

A division bench comprising Chief Justice NV Anjaria and Justice KV Aravind ruled that the NGT's order, which imposed an environmental compensation of ₹2.94 crore on MEG, was issued without granting them an opportunity to be heard, violating principles of natural justice.

The court has remanded the case back to the NGT, Southern Zone, Chennai, for reconsideration. The NGT has been directed to decide afresh on the imposition of environmental compensation after providing a fair hearing to MEG.

However, the High Court ordered MEG to deposit ₹1 crore with the Karnataka State Pollution Control Board (KSPCB) as per the August 2024 NGT directive. This deposit will remain subject to the outcome of the fresh proceedings.

The NGT initiated the case in March 2016 following a news report that alleged pollution by a slaughterhouse, MEG, and the Bengaluru Water Supply and Sewerage Board (BWSSB). The BWSSB was also directed to pay ₹1 crore as environmental compensation.

Additional Solicitor General Arvind Kamath, representing MEG, argued that an open stormwater drain under BWSSB flows through MEG’s premises into the lake, contributing to the pollution. He stated that the sewage load from MEG is minimal and plans for a 1,200-KLD sewage treatment plant (STP) are underway.

The bench noted that no proper liability assessment had been conducted against MEG, and no opportunity was provided for them to present their defence before the demand notice was issued.

The matter will now be re-examined by the NGT.