Ranchi (PTI): The High Court refused to put a stay on proceedings against three suspended Congress legislators, who were arrested from Kolkata in July, for their alleged involvement in ferrying cash.

After hearing the matter of Irfan Ansari, Rajesh Kachhap and Naman Viksal Kongari, accused of laundering cash to the tune of around Rs 48 lakh, the court of Justice Sanjay Kumar Dwivedi on Friday declined to put a stay on the investigation.

However, it directed that chargesheet in the case may not be filed until orders of the court are passed.

The Congress had in July suspended the three Jharkhand MLAs, who were allegedly caught with huge amount of cash in West Bengal's Howrah, and accused the BJP of attempting to topple its coalition government in the state.

Acting on a tip-off, the West Bengal Police had intercepted a sports utility vehicle in which the legislators were travelling, and allegedly found nearly Rs 50 lakh in cash in the car.

Congress MLA Anup Singh had filed a case against the three legislators in Argora Police Station, which was transferred to Kolkata.

The three MLAs had moved the Jharkhand High Court, challenging the transfer of the FIR from Ranchi to Kolkata.

The case will again be heard on November 10.

Let the Truth be known. If you read VB and like VB, please be a VB Supporter and Help us deliver the Truth to one and all.



Mangaluru (Karnataka) (PTI): The KPTCL has set a target to complete the strategically important Kadandale 400 kV power substation project by July 15, aiming to ensure uninterrupted and quality power supply to the coastal districts of Dakshina Kannada and Udupi, officials said on Wednesday.

The target has been fixed by the KPTCL (Karnataka Power Transmission Corporation Limited) following the directions of State Energy Minister K J George, they said.

The project, located at Kadandale village in Moodbidri taluk of Dakshina Kannada district, had remained stalled for nearly three years due to land-related litigation affecting the 400 kV transmission line works, officials said.

However, the hurdles were successfully resolved through the sustained efforts of Energy Minister George and Energy Department Additional Chief Secretary Gaurav Gupta, they said.

Following the minister's directions, KPTCL Managing Director Ram Prasath Manohar visited the project site on Wednesday to review the progress of the works, according to an official statement.

"Mangaluru is one of Karnataka's key industrial hubs and requires a reliable and uninterrupted power supply. As directed by the Hon'ble Minister, we are working towards completing the project before the onset of the monsoon and commencing transmission operations at the earliest," Manohar said.

According to officials, the Kadandale 400 kV substation is expected to significantly strengthen the power infrastructure of Dakshina Kannada and Udupi districts, which are major industrial and commercial regions of the state.

Manohar said the project would provide a long-term solution to recurring monsoon-related voltage fluctuations and low-voltage issues in the coastal belt.

"The new substation will improve grid stability and ensure quality power supply to the region. In the event of a technical fault in any one station, load can be quickly diverted through this substation, enabling faster restoration of electricity supply," he explained.

To expedite completion of the project, KPTCL has planned to obtain line clearance on the existing 400 kV UPCL-Hebbanahalli transmission corridor between May 6 and May 24, 2026, the statement said.

During this period, alternative arrangements have been made to manage transmission loads and maintain supply based on demand conditions, it said.

However, officials stated that short-duration load shedding may become unavoidable under technically exigent situations.

"This project is crucial for the long-term energy security of Mangaluru and the coastal region. We request consumers and the public to extend their cooperation during this temporary operational phase," the KPTCL MD stated.

Minister George said that ensuring uninterrupted power supply for the benefit of the public and the industrial growth of the coastal region is one of the government's top priorities.

"Due to certain legal hurdles, the 400 kV transmission line work was delayed. The department has taken special initiative to resolve these obstacles. The Kadandale substation will ensure high-quality power supply for Mangaluru and Udupi regions," he said.

"The department continuously monitored the land-related disputes affecting the project and ensured timely resolution through coordinated intervention. KPTCL has been instructed to complete the works within the stipulated timeline and dedicate the project to public service at the earliest," Gupta stated.