Mangaluru: A barrier constructed for the waterfront project on the banks of the Netravati River has collapsed near Mulihithlu, causing significant public outrage. This incident occurred even as the National Green Tribunal (NGT) in Chennai stayed the project's work following opposition from environmentalists and locals.

Deputy Commissioner Mullai Muhilan has ordered an investigation into the collapse. Assistant Commissioner Raju K. stated that notices will be issued to the supervising officers, and payments to the contractors responsible for the construction will be withheld pending further inquiry.

The Netravati River Front (waterfront) project, stretching 2.1 km from Morgansgate to Bolar, developed by Mangalore Smart City Limited, aims to transform the area into a walking area. As part of the project, a barrier wall was constructed along the riverbank and soil filling was carried out. However, heavy rains last week caused a section of the barrier near Mulihithlu to collapse.

Smart City officials reported that 1,200 meters of the project has been completed, with some areas filled with soil. These sections were intended to be leveled with a roller. Unfortunately, water infiltrated one part of the project, creating a pit and leading to the collapse of the barrier wall. Officials have stated that the contractor responsible for the construction will be questioned regarding the incident.

Arun Prabha, Senior Officer of the Siruva Smart City Project, assured that such problems would not recur.

The project spans 2.1 km, but currently, work is ongoing only up to 1,600 meters. Local opposition has led to court cases concerning the remaining sections, indicating that the project's completion is contingent on resolving these issues.

Environmentalists have expressed strong opposition. The National Green Tribunal (NGT) has been approached by the NECF alleging violations of environmental norms related to the Netravati waterfront project. The NGT has registered a case and issued a notice to the district administration and the relevant committee to investigate these allegations. Both the committee and the district collector have conducted site inspections. Meanwhile, the collapse of the barrier wall has bolstered the objections of locals and environmental activists, strengthening allegations of regulatory violations.

Following the NGT order, a joint committee arrived to inspect environmental norm violations in the project area. The Deputy Commissioner had also visited the project area. However, the NECF, which filed the complaint with the NGT, was not informed or provided with the opportunity to present documents for verification. Smart City officials, along with some project supporters, were called for inspection instead. This has led to dissatisfaction among activists of the National Environment Care Federation (NECF), who are unclear about the nature of the project.

The site of the barrier wall collapse will be visited and inspected, and the engineers and officials responsible will be called and cautioned to carry out their work diligently. A notice regarding the collapse will also be issued to the concerned parties. The investigation is currently underway by the NGT, and work will resume only after obtaining permission from the NGT.

Raju K., Assistant Commissioner, Mangaluru

A bridge in Bihar collapsed before its inauguration. This project, undertaken by people’s representatives in a district known for its intelligent population, risks losing hundreds of crores of rupees. What is the story behind this spending plan if the barrier collapses after a few days of rain? The project is being carried out flouting all environment laws. Even before the inauguration, the barrier has collapsed. Despite the apparent looting of the environment and people's tax money, the concerned authorities remain silent. Fake activists are working to cause trouble against those legitimately opposing it.

Shasidhara Shetty, Convenor, NECF

The Netravati WaterFront Project was initially estimated at Rs. 70 crore but has since been revised and sanctioned for Rs. 32 crores. The project covers a distance of 2.1 km and is designed for non-motor vehicle use, with facilities for cycling and other amenities for public enjoyment. Arun Prabha, a senior officer of Smart City Limited informed that currently, 5% of the work, amounting to Rs. 5 crore, has been completed, and the contractor has been paid Rs. 2,42,18,650.

Let the Truth be known. If you read VB and like VB, please be a VB Supporter and Help us deliver the Truth to one and all.



ISLAMABAD: At least two more cases of poliovirus were reported in Pakistan, taking the number of infections to 52 so far this year, a report said on Friday.

“The Regional Reference Laboratory for Polio Eradication at the National Institute of Health has confirmed the detection of two more wild poliovirus type 1 (WPV1) cases in Pakistan," an official statement said.

The fresh infections — a boy and a girl — were reported from the Dera Ismail Khan district of Khyber-Pakhtunkhwa province.

“Genetic sequencing of the samples collected from the children is underway," the statement read. Dera Ismail Khan, one of the seven polio-endemic districts of southern Khyber Pakhtunkhwa province, has reported five polio cases so far this year.

Of the 52 cases in the country this year, 24 are from Balochistan, 13 from Sindh, 13 from Khyber Pakhtunkhwa, and one each from Punjab and Islamabad.

There is no cure for polio. Only multiple doses of the oral polio vaccine and completion of the routine vaccination schedule for all children under the age of five can keep them protected.