Howrah/Kolkata (PTI): India's first underwater tunnel, being built under the Hooghly River in West Bengal at a cost of around Rs 120 crore as part of the East West Metro Corridor, will be a blink-and-you-miss-it experience for passengers as trains will cross the 520-metre stretch in just 45 seconds.
The tunnel -- the Indian version of Eurostar's London-Paris corridor -- is 13 metre below the riverbed and 33 metre below ground level.
The 520-metre tunnel is part of the East West Metro Corridor of Kolkata -- from the IT hub of Salt Lake Sector V in the east to Howrah Maidan in the west across the river.
The tunnel's construction is complete and is likely to be commissioned in December 2023 after the completion of a 2.5-km stretch between Esplanade and Sealdah on the corridor.
"The tunnel is essential for the East West Corridor and it was key. The under-the-river-alignment was the only alignment possible with residential areas and other technical issues involved," said Kolkata Metro Rail Corporation General Manager (Civil) Sailesh Kumar.
"This metro route between Howrah and Sealdah cuts down the commute time to 40 minutes as against 1.5 hours by road. It will also ease congestion at both ends," he said.
It will take 45 seconds to cross the tunnel, he said.
The East West Corridor of the metro rail has been marred by delays and resultant cost escalations. It was approved in 2009 at a cost of Rs 4,875 crore and a completion date of August 2015. According to officials, the cost has now increased to Rs 8,475 crore out of which Rs 8,383 crore has already been spent.
The tunnel will have an internal diameter of 5.55 metre and an external diameter of 6.1 metre. The spacing between the up and down tunnels will be 16.1 metre centre-to-centre.
The inner walls of the tunnel are being made with high quality M50 grade, reinforced concrete segments with a thickness of 275mm each. Six of these segments will complete a circular lining of the tunnel's diameter. The segments are being pre-cast in specialised moulds imported from Korea.
Several protective measures have been taken to prevent water inflow and leakages in the tunnel. Concrete mixes composed of fly ash and micro silica have been used for the segments to minimise water permeability.
The segments are being sealed using a complex grouting process that will fill the space between the segments and the shield of the tunnel boring machine (TBM).
A two-component grout mix, including a slurry made of water, cement and bentonite and sodium silicate, is being used to fill the gaps. The liner segments are fitted with German-made neoprene and hydrophilic auxiliary gaskets, which expand when in contact with water to prevent inflow through segmental joints.
Two German-made tunnel boring machines (TBMs), named Prerna and Rachna, were deployed for the process.
Emergency evacuation shafts up to 760 metre in length are being provided inside the tunnel in accordance with the National Fire Protection Association (NFPA) guidelines. The evacuation shafts are being provided in Howrah Station in the west and Strand Road in the east for passenger safety.
Let the Truth be known. If you read VB and like VB, please be a VB Supporter and Help us deliver the Truth to one and all.
New Delhi: The government on Wednesday further tightened wheat stock holding norms for wholesalers, small and big chain retailers, and processors to curb hoarding and check price rise.
"As part of continuous efforts to moderate prices of wheat, the central government has decided to revise the wheat stock limit applicable until 31st March 2025," the food ministry said in a statement.
According to the revised norms, wholesalers are now allowed to maintain wheat stock up to 1,000 tonne instead of 2,000 tonne, retailer can hold 5 tonne for each outlet instead of 10 tonne, while big chain retailer can hold 5 tonne for each outlet instead of 10 tonne earlier.
Processors will be allowed to maintain 50 per cent instead of 60 per cent of their monthly installed capacity multiplied by the remaining months till April 2025.
The stock limits on wheat were first imposed on June 24 and later revised to tighten the norms on September 9 in order to manage the overall food security and to prevent hoarding and unscrupulous speculation.
The ministry said all wheat stocking entities are required to register on the wheat stock limit portal (https://evegoils.Nic.In/wsp/login) and update the stock position every Friday.
If the stocks held by entities are higher than the prescribed limit, they should bring the quantity to the prescribed stock limits within 15 days of the issue of the notification.
Any entity which is found to have not registered on the portal or violates the stock limits will be subject to suitable punitive action under the Essential Commodities Act,1955.
The food ministry is maintaining close watch over the stock position of wheat to control prices and ensure easy availability in the country.