Bengaluru, Aug 11: Karnataka Infrastructure Development Minister M B Patil on Friday said the work on the Bengaluru Suburban Rail Project corridor-2 between Benniganahalli and Chikkabanavara (25.01 km) will be completed within the set deadline of the next 26 months.
The Minister spoke to reporters after inspecting the progress of work along with Energy Minister K J George and K-RIDE officials. He also visited Lingarapuram, Shampura, Hebbal and Yeshawantpur.
"The BSRP project which runs parallel to the existing South-Western Railway lines has its challenges. However, these will be resolved to ensure completion of the project within 26 months," Patil said.
ALSO READ: K'taka Deputy CM DK Shivakumar says he will retire from politics if it is proved he took commission
The Minister said the officials have been instructed to work towards completing the works related to all four corridors by 2026. Even if it gets delayed due to some unforeseen reasons the project would be ready by 2028, he added.
According to him, the BSRP requires 157 acres of Railway land. He further said existing encroachments and structures on Railway land are being removed. Private land of about 5.11 acres required for laying of tracks has been acquired. Government land of about 2.72 acres has been acquired out of the total 7.73 acres.
Patil said Defence land of about 7.38 acres is required at three locations Jalahalli, Nagawara, and CQAE near Yeswanthpur. Working permission and in-principle approval has been obtained for these three locations from Defence Authorities.
Physical possession is yet to be handed over to KRIDE, Patil explained.
"So far, 10 to 15 per cent of work has been achieved related to corridor-2 and ground works will be over in the next 10 months. The ongoing RUB (Railway Under Bridge) at Shampura will also be completed by then," the minister explained.
After completing Corridor-2, works related to Corridor-3 between Bengaluru and Devanahalli Airport and Corridor-4 between Kengeri and Whitefield will be taken up, Patil said.
He said a proposal has been sent to extend the BSRP to Chikkaballapura, Mysuru, Magadi, Tumakuru, Gowribidanuru, Kolara, and Hosuru. If this gets approved the BSRP would expand to a length of 452 km. Approval has been sought from Railways Department to conduct a pre-feasibility study regarding this.
Tenders have been invited to construct 12 stations under EPC mode (Engineering, Procurement, Construction) along the stretch of corridor 2 and the tender process will be finalised on August 31, Patil said.
The tender process for civil works of corridor-4 is over and bidders will be awarded the works soon. Supply of the first batch of 10 trains will begin in October. 2025, he added.
Let the Truth be known. If you read VB and like VB, please be a VB Supporter and Help us deliver the Truth to one and all.
Budapest/Washington: US Vice President J D Vance has said that Lebanon was never included in the ceasefire understanding with Iran, describing the confusion as a “legitimate misunderstanding”.
Speaking to reporters before departing from Hungary, Vance said, “I think the Iranians thought that the ceasefire included Lebanon and it just didn’t. We never made that promise.”
He stressed that the United States had not included Lebanon in the scope of the ceasefire at any stage.
His remarks come amid continued Israeli strikes in Lebanon, where more than 200 people were reported killed, even as ceasefire talks between Iran and the US move forward.
Vance said Israel had “offered … to check themselves a little bit in Lebanon because they want to make sure that our negotiation is successful”.
He warned that if Iran allows the situation in Lebanon to affect the negotiations, it could derail the talks.
“If Iran wants to let this negotiation fall apart in a conflict where they were getting hammered over Lebanon, which has nothing to do with them and which the United States never once said was part of the ceasefire, that’s ultimately their choice,” he said.
